Ranking of Project Delay Factors in the Construction of Civil Infrastructure, Case study: Tehran Highway Bridge

Document Type : Research Paper

Authors

1 Ph.D. of Earthquake Engineering, Researcher of Bonyad Melli Nokhbegan, Tehran, Iran

2 M.Sc. Student of Engineering and Construction Management, University of Civil Engineering and Development, Hamedan, Iran

Abstract

Purpose of this study is Assessment and review of time - lag factors in a Bridge. The execution of development projects such as bridges, due to the importance and critical role of the structure in the system of transport and traffic control, aims at achieving the goals of development plans and its impact on the development and evolution of human activities, distribution of services and reducing traffic volume, as compared to other development projects. It is essential to study the factors of time delay in the construction process, and thus making significant savings in the construction and implementation of other similar development projects, thus making significant savings on the financial and temporal dimensions. In this study, after accurate identification and introduction of case study , three main indices of project delay , each consisting of several sub - branches , are prepared in the majority of questionnaires and are weighted by a number of experts , indicators and sub - indices of project delay. In this way, the most important parameters which have the maximum contribution to the delay in the project implementation process are introduced. In the following, using the classification and gathering points and the results of the questionnaire, the most important factors for delay in the project will be identified and introduced. It should be noted that the responses obtained from the questionnaire in this study will be AHP method. According to the results of the present study, one of the most important factors affecting the time delay regarding the bridge has been classified into three main indicators related to financial factors, regulatory factors and executive management factors. Therefore, the most important sub - indicator of the delay was due to the three indicators of financial , monitoring and implementation, respectively, lack of price list nonuse of new engineering contracts such as BOO , BOT , EPC  and lack of Article 53 of the General Terms of treaty.

Keywords


[1]-Khodabakhshi, G.A., Hosseinalipour, S.M., and Shafia, M.A.,2005, Indentifying the effective factors in delaying the construction projects of chaharmahal and bakhtiari treatment plants, Master Thesis, Shahid Beheshti University, (In Persian).
[2]-Fahimiazad, H., Abrishami, J., and Kazemi, M., 2001, Indentifying the causes of delays and consequences due to non-timely delivery of dams in Khorasan province, Master Thesis, Institute of Management Research and Training, (In Persian).
[3]-Yousefian, B., Hosseinalipour, S.M., and Naghshi, A., 2002, Identifying the effective factors in delaying the transmission line and distribution line projects of the electricity company , Master Thesis, Institute of Management Research and Training, (In Persian).
[4]-Vatankhah, R., Bemanian, M., and Parvizian, K., 2002, Investigating the causes of delays in construction projects Acase study of the projects of the School Renovation Organization of the country , Master Thesis, Tarbiat Modares University, (In Persian).
[5]-Moinpour, B., 2017, Factors affecting project delays , The first specialized conference on project claims management, Tehran University, (In Persian).
[6]-Ghoreyshian, S.M., and Khoshfetrat, A., 2016, Investigating the role of factors in delaying urban projects , 3rd International Conference on Applied Research in Civil Engineering, Architecture and Management, Tehran, (In Persian).
[7]-Mirzarasolzadeh, T., and Bezaati, R., 2018, Predicting the reduction of construction project delays due to re-engineering in Ardabil Oil Company , Conference on Civil Engineering, Architecture and Urban Planning of the Islamic World, Tabriz, (In Persian).
[8]- Al Humaidi, a., and Tan, H,. 2010, A fuzzy logic approach to model delays in construction projects using rotational fuzzy fault tree models, International Journal of Project Management 32.
[9]-Bib, J., Mei-Yi, Y., and Kuei, C., 2013, An empirical study of schedule delay causes based on Taiwans Litigation case, Journal Construction Industry.
[10]-Nielsen, G., and Ozdemir, H., 2013, Quantification of delay factors using the relative importance index method for contruction projects in Turkey, Master Thesis, Olabia University.
[11]- Saaty, T.L., 1980, The Analytic Hierarchy Process, McGraw Hill, New York, 1980.